New York Global wafer plant has been dragged down infrastructure
fecha:2010-11-09 16:32
key supporting infrastructure, the other 17 units have been completed and is currently short of a natural gas pipeline, the main road entrance of the cooling Road, a road and secondary sources.
Needed before the two were about 1,000 million dollars and 700 million U.S. dollars, but the Luther Forest Technology Park Economic Development Corporation made this application to the state government, but has not been approved.
Currently, the New York State Government intends to take over the Luther